Table 4: Costs associated with decommissioning of the Finlayson dam
Item |
Remarks |
Price (Year 2000 $C) |
Price (Year 2000 $US) |
Mobilisation and demobilisation |
Lump sum |
$50,000 |
$33,385 |
Demolition |
About 400 m3 |
$80,000 |
$53,415 |
Fish habitat enhancement works |
Sweeper trees, log boulder clusters, root fans |
$23,000 |
$15,357 |
Shoreline stabilisation works |
Live stakes, seeding, bank stabilisation |
$11,100 |
$7345 |
Engineering, construction supervision and environmental assessments |
Design, tendering, civil/environmental site supervision |
$80,000 |
$53,415 |
Post construction environmental monitoring |
Site monitoring in 2001 and 2002 |
$10,000 |
$6667 |
|
TOTAL |
$254,100 |
$169,660 |
|