Table 2: New Turkish hydroelectric generating capacity 2005-09
Name of scheme |
Province |
Installed generating capacity (MW) |
Annual generation (GWh) |
Year completed or scheduled |
DERINER** |
ARTVIN |
670 |
2,118 |
2008 |
ERMENEK** |
KARAMAN |
309 |
1,187 |
2007 |
BORÇKA** |
ARTVIN |
300 |
1,039 |
2007 |
OBRUK |
ÇORUM |
200 |
473 |
2007 |
ALPASLAN-I |
MUSS |
160 |
488 |
2007 |
KIGI |
BINGÖL |
140 |
423 |
2009 |
ULUBAT- ÇINARCIK* |
BURSA |
120 |
548 |
2009 |
AKKÖPRÜ |
MUGLA |
115 |
343 |
2007 |
MURATLI** |
ARTVIN |
115 |
444 |
2005 |
TORUL |
GÜMÜSHANE |
103 |
322 |
2006 |
KÖPRÜBASI |
ZONGULDAK |
74 |
203 |
2008 |
UZUNÇAYIR |
TUNCELII |
71 |
317 |
2007 |
TOPÇAM |
ORDU |
60 |
200 |
2007 |
KILAVUZLU |
K.MARASS |
57 |
100 |
2007 |
SANLIURFA –TÜNEL |
SANLIURFA |
50 |
124 |
2005 |
ÇINE |
AYDIN |
40 |
118 |
2007 |
DIM |
ANTALYA |
38 |
123 |
2007 |
CINDERE |
DENIZLII |
29 |
88 |
2007 |
MANYAS |
BALIKESIR |
20 |
59 |
2007 |
SÜREYYABEY |
YOZGAT |
14 |
50 |
2008 |
KIRAZLIKÖPRÜ |
KASTAMONU |
12 |
41 |
2008 |
KUMKÖY |
SAMSUN |
10 |
65 |
2006 |
BOGAZKÖY |
BURSA |
10 |
20 |
2008 |
ATASU |
TRABZON |
5 |
27 |
2009 |
TOTAL |
|
2,722 |
8,920 |
|
Source: General Directorate of State Hydraulic Works (DSI)
* Developed by private sector companies under licence from EPDK (Energy Market Regulatory Authority).
** Being built under an intergovernmental agreement.
|