Table2: Plinth concrete quantities
Stage No / Access Route |
Elevation |
Start date |
Finish date |
Qtty. (m3) |
Phase 2, Access Road 1 |
388 |
25 Mar 2004 |
28 Apr 2004 |
1382 |
Phase 1, Access Road 2 |
335 |
18 Mar 2004 |
20 Jul 2004 |
1942 |
Phase 3, Access Road 3 |
269 |
11 May 2004 |
22 Sep 2004 |
1252 |
Phase 4, Access Road 4 |
222 |
20 May 2004 |
07 Oct 2004 |
2754 |
Phase 5, Platform Mat.3B |
229 |
08 Nov 2004 |
29 Nov 2004 |
1217 |
Phase 6, Access Road 5 |
322 |
06 Dec 2004 |
24 Jan 2005 |
600 |
Phase 7, Access Road 5 |
322 |
01 Feb 2005 |
01 Apr 2005 |
258 |
Phase 8, Access to Intake |
396 |
02 Apr 2005 |
15 May 2005 |
135 |
Total Concrete (m3) |
|
|
|
9540 |
|