Siemens Power Generation Group (Siemens PG) will upgrade the high- and intermediate-pressure turbines and two low-pressure turbines at units G and H of the 620MW coal-fired power plant, which came online in the mid-1970s.
Siemens also said that the scope of its services will include further efficiency enhancement measures, such as modernization of the condensers and the turbine I&C systems. The modernization work is due to be completed in 2008 and 2009.
Siemens reported that, as a result of the advanced turbine technology, the plant’s carbon dioxide emissions will be reduced by 600,000 tons per annum, even though the facility will generate the same amount of electricity.
Compared to new construction projects older power plants can be adapted more rapidly to future market conditions through customized modernization packages, said Harald Griem, head of the service product line at Siemens PG.
Mr Griem added: These measures not only increase plant efficiency and availability but also enhance operating economy and environmental friendliness.