As per the contract, the West African oil and gas services firm will install a produced water handling module and four living quarters modules on its FPSO vessel.

The total weight of the M12 produced water module is approximately 300 short tons.

The work is expected to be executed during the second quarter of 2011 using the Jascon 25 DP3 offshore construction vessel and will take approximately 15 days including mobilization and demobilization.