Pre-feasibility studies

(i) includes contingencies of 10% on the civil works, moving sections of the road, anticipated expropriation costs and transmission grid connection.

Licence Project site Water level (m asl) Gross head (m) Discharge (Qins( (m3/sec) Capacity (MW) Output (GWh/yr) Construction cost (EURM) (i)
Brodarevo 1 Junakovina 519 19.73 150 26 102.33 71.099
Brodarevo 2 Lucice 488 24.7 150 32.4 130.59 68.83