Under the contract, MHPS will be responsible for large-scale replacement of core components of the plant’s seriously degraded power generation facilities.
Located in the city of Basra in south Iraq, the Hartha thermal power station involves both gas- and oil-fired units and the original equipment was developed by Mitsubishi Heavy Industries (MHI).
The refurbishment work, which is planned to be completed in May 2017, will enable the unit to restore its original rated output.
MHPS will replace core equipment of the Unit 4 which includes boilers, steam turbines and generators as well as install a new distributed control system (DCS), in order to significantly enhance reliability of the power station.
GAMA Power Systems Engineering and Contracting will be responsible for installation and other work at the site.