Liberty Energy, an oil and gas exploration and production firm, has completed the final phase of the work on the Dahlstrom #1 well in Texas, US.

The company scheduled a cement squeeze to be performed on the well and this procedure was designed to plug the lower zones of the well with cement.

The well was then re-perforated at a higher interval, thus isolating the higher productive perforation, in order to impede any water from encroaching into the productive zone.

Following the completion of the squeeze, the company re-perforated the well at a higher perforation to produce from the well and also reduce the possibility of any water encroaching on the productive zone of the well, which is expected to go online this week.