The Feasibility Study indicates that the Coffee Project represents a robust, rapid pay-back, high margin, ten year open pit mining and heap leach project that works in the current gold price environment.

As such, Kaminak intends to move forward into mine permitting to support mine construction, which is planned for mid-2018. The Company is well financed ($28 million as of September 30, 2015) to undertake an aggressive work-plan in 2016 to meet these objectives.

At a gold price of US$1,150/oz and an exchange rate of C$1.00 to US$0.78, the Coffee Project base case estimate (the "Base Case") generates an after-tax net present value (NPV) at a 5% discount rate of C$455 million and an internal rate of return (IRR) of 37%.

The proposed mine will operate over an initial ten year mine-life with average annual gold production in excess of 200,000 ounces for the first five years (excluding the initial 3 month ramp-up period), and average annual life-of-mine gold production of 184,000 ounces.

Initial capital expenditure to fund construction and commissioning is estimated at C$317 million, with a life-of-mine capital cost of C$478 million (including C$60 million in closure costs). The all-in sustaining cash costs (as defined per World Gold Council guidelines, less corporate G&A) is estimated to be US$550 per ounce of gold produced.

The project is expected to have a significant impact on Yukon’s GDP, generating over $2 billion of gross revenue and contributing 480 permanent, high paying jobs.

Eira Thomas, Kaminak President and CEO commented: "This feasibility study firmly establishes the Coffee Project as one of the world’s best undeveloped gold projects by value and margin that works in the current gold-price environment.

"The Coffee Project further benefits from being a simple, open pit, heap leach mining opportunity, situated near infrastructure that delivers low all in sustaining costs and pays back capital in under two years". She further noted, "Kaminak feels privileged to be working in the pro-mining jurisdiction of Yukon where we enjoy strong relations with all levels of government, including our local First Nations, with whom we have worked alongside, collaboratively since 2010."

Furthermore, Kaminak is hosting a live Q&A conference call on Thursday, January 7th at 11:00 a.m. Eastern time (8:00 a.m. Pacific time) with the Kaminak Executive and Feasibility Study team. Participants may join the call by dialing toll-free North America (866) 393-4306 or International (734) 385-2616 and providing the company name (Kaminak Gold Corporation) to the operator.

A recorded playback of the call will be available two hours after the call’s completion until January 21st, 2016 by dialing (855) 859-2056 and entering the conference ID#: 17824557, and on the Kaminak website.

The Feasibility Study was initiated in July 2014 after the release of the Preliminary Economic Assessment in June 2014 and commenced with infill drilling, geotechnical investigations and other fieldwork to support the study.