According to the contract, Acteon will design, fabrication and install 12 suction pile anchors, pre-set installing of 12 chain/polyester/chain mooring lines and hook-up of the LLOG Delta House production semi-submersible (the floating production system "FPS").

InterMoor plans to start installation activities in mid-2014, while Delta House is LLOG’s second Exmar-designed Opti deep-draft, semi-submersible production system in the region.

InterMoor president Tom Fulton said the approach to the award process include comprehensive engineering, design, fabrication and installation procedures and plans, as well as preparing a detailed proposal that broke out each phase of the work scope.

"This project will add to InterMoor’s already strong track record for permanent moorings which includes some of the largest deepwater mooring projects around the world, including Kikeh, Shell Auger, ATP Mirage and the Williams Gulfstar FPS," Fulton added.