The facility will also have associated electric transmission facilities in Hardin and Logan counties.
The Scioto Ridge project will be constructed across 17,000 acres of leased private land in Lynn, McDonald, Roundhead, and Taylor Creek townships in Hardin County and Richland and Rushcreek townships in Logan County.
According to OPSB, the wind farm is associated with two additional OPSB cases entailing the construction of a 4.8 mile long 345kV transmission line as well as a 345kV substation in McDonald Township.
With a nameplate capacity of up to 300MW of electric generation, the wind farm will include up to 60 miles of access roads.
The project will also include 83 miles of underground electric collection lines, four meteorological towers, turbine structures and electric transmission facilities.