Under the contract, Gamesa will supply, install and commission 50 G97-2.0MW turbines at the wind farm in Zhangjiakou, in the province of Hebei.

The company is scheduled to deliver the turbines during the third quarter of this year. The wind power plant is planned for commissioning the following quarter.

The contract value was not disclosed.

Ealier this year, Gamesa received two wind turbine contracts, totaling 92MW, in China.

Under the first contract, Gamesa will supply, install and commission 25 G97 2MW turbines at the Nandianziliang wind complex, which is being developed by HCIG in the Shanxi province, northern China.

Under a separate contract with Chinese wind farm developer, UPC, Gamesa will supply, install and commission 21 G97 2MW turbines at the Huangyan wind farm in the province of Zhejiang, eastern China.

Gamesa has installed more than 3,626 MW in China, and has nearly 900MW under maintenance.