This program will cover nearly 472 samples at 400m x 400m spacing and should get underway in late April May 2012. The sampling program is expected to take 30-40 days for completion .

At Mooloogool, works will commence on E51/1367 which will include a 15 hole Air Core program for drilling l to 100m in depth with the holes spaced 1km apart.

A soil sampling program is also carried out at Mooloogool/Diamond Well to investigate various new targets which cover 10 tenements.

The targets will include 4,330 soil sample for 216 line kilometres, and 15 drainage samples including geological mapping and scintillometer readings.

Dourado is also undertaking a number of projects in the prospect, including the Sabbath Gold Project and the Garden Gully projects.

At Sabbath, currently the RC program of 124 holes for 15,000m has commenced and is moving ahead after the tail end effects of cyclone Lua that delayed the work by 2 weeks.

Under the first phase, 13 holes are drilled for total of 1,551m and all the samples are submitted to the lab for analysis.

Data from the resource drilling of Sabbath/Garden Gully Projects confirmed high grade, near surface mineralization in several south-plunging shoots and a proposed 15,000 metre RC program is underway.