Located in the Zhangbei, Hebei Province, the utility project combines 140MW of renewable energy generation (both wind & solar), 36MWh of energy storage and a smart power transmission system.
The $500m first phase of the project includes 100MW of wind, 40MW of solar and 36MWh of battery.
Furthermore, the State Grid system is demonstrating a stable solution for transferring huge amounts of renewable electricity safely to the grid on an unprecedented scale.
SGCC has chosen BYD’s Iron-Phosphate battery technology and its peak shaving, load leveling charge and discharge methodologies.
This new project designed by SGCC, is part of the national Golden Sun program and with the State Grid has outpaced other grid projects in China.
BYD’s battery energy storage system provides a solution for the realization of energy storage in the smart grid that improves renewable energy efficiency by 5%-10%.