Breakdown of the scheme’s overall costs
|
Item |
Cost |
% of total |
Consultancy costs |
|
|
(Includes: feasibility study, topographic and river surveys, ground investigations, consultations, environmental assessment, reporting, design, etc) |
£599,000 (US$943,063) |
10.8% |
|
|
|
Environmental agency costs |
£414,000 |
7.5% |
(Includes: client costs, environmental inputs, ECC Project Manager, landowner compensation) |
(US$651,792) |
|
|
|
|
|
|
|
Site supervision |
|
|
(Includes: ECC Supervisor and staff) |
£329,000 (US$517,970) |
5.9% |
|
|
|
|
|
|
Construction |
|
|
(Includes: out-turn, including |
£4.2M (US$6.6M) |
75.8% |
compensation events) |
£5.5M (US$8.7M) |
100.0% |
|
|