With this, the company has commissioned a total of five units at the 412MW hydro power plant of SJVN Limited.
The company has commissioned earlier four units between March 2014 and June 2014 and have been been put into commercial operation.
BHEL is likely to commission the sixth and last unit shortly and is in an advanced stage of execution.
BHEL’s scope of work in the project includes supply, erection and commissioning of six numbers 68MW Francis turbines operating at a head of 119m with matching synchronous generators of 200rpm, static excitation system, main inlet valves, digital governors, state-of-the-art control & monitoring system (SCADA), associated station auxiliaries, gas insulated switchgear (GIS) and electrical & mechanical balance of plant (BoP).