The 600MW HVDC transmission line between Tasmania and the Australian mainland in Victoria has begun full commercial operations.

The 360km interconnection, currently the world’s longest such link, has been repeatedly delayed, most recently after electrical equipment was damaged in rough seas during transport from Germany. Its completion will allow Hydro Tasmania to enter the national electricity market, using its abundant hydro resources to bolster capacity during the mainland’s peak summer demand period.

Hydro Tasmania chief executive Geoff Willis said: ‘I congratulate Basslink’s owner, National Grid, for achieving this project of national significance. Basslink went through the most rigorous approval process for any major energy project in Australia’s history.’

An official opening ceremony for Basslink is planned for mid-May.


Related Articles
Basslink operating successfully for Tasmania
Basslink eases impact of Tasmanian winter