The draft was prepared on the basis of the recommendations of a working group made up of representatives from state institutions and business associations

21137_5dc86b6a46cc74e75f1e9ac1060ddd14

Ministry of Energy prepares proposals for wind farms in Baltic Sea. (Credit: Government of the Republic of Lithuania)

The Ministry of Energy has submitted a draft Government Resolution to stakeholders for coordination on locations in the Baltic Sea where it is expedient to develop wind farms. Proposals were also submitted regarding the capacities of the power plants – it could meet one-quarter of Lithuania’s demand.

“Conditions for the development of onshore wind energy have already been created, and this is now another step forward – creating a favourable environment for wind energy in the Baltic Sea. Offshore wind will be a new and significant turning point in Lithuanian energy, as electricity generation from offshore wind is more efficient and has greater potential than onshore. Fierce competition will begin for investment in this area, and we need to be as well prepared as possible for this,” says Minister of Energy Žygimantas Vaičiūnas.

The draft was prepared on the basis of the recommendations of a working group made up of representatives from state institutions and business associations. Formed by order of the minister, the working group examined the following key issues: possible stages of wind turbine development in the Baltic Sea, models for connecting the turbines to power grids, distribution of responsibilities and connection costs, selection of locations for the turbines in marine territory, and research that must be done. Also considered were possible methods of support, regulation of permits to use territorial waters, and development of the offshore wind equipment supply chain.

Taking into account the objectives of the National Energy Independence Strategy and the National Energy and Climate Plan as well as the recommendations of the working group, the draft Government Resolution envisages that the installed capacity of the wind farm would reach 700 MW. A wind farm of this capacity in the Baltic Sea would produce approximately 2.5-3 TWh of electricity per year, which is 25 per cent the country’s current electricity demand.

The exact territory of the Baltic Sea where the development of wind turbines would be most efficient is provided for in the resolution. The territory planned in the Baltic Sea covers an area of 137.5 km2, with a distance from shore of approximately 29 km, an average water depth of 35 m, and an average wind speed of approximately 9 m/s.

At present, legislation does not provide for a support scheme for the construction of offshore power plants. It is proposed to entrust the Ministry of Energy with preparing the necessary bills regulating the support scheme for power plants to be developed in Lithuania’s territorial waters and coordinating the proposed support scheme with the European Commission by 1 June.

Considering that it may take up to eight years to install the networks connecting the offshore power plants, the development of these networks should be initiated as soon as possible. It is therefore proposed to charge the transmission system operator Litgrid with beginning preparatory work.

The first auctions for offshore wind are planned to be announced in 2023. The power plants should be built and start generating electricity by 2030.

The development of offshore wind is one of the goals of the Government’s programme. The programme calls for the potential, need for development and costs of wind energy in the Baltic Sea to be evaluated, and for decisions to be made on the development of wind turbines in the Baltic Sea.

Source: Company Press Release