As part of the order, Vestas has agreed to deliver eight units of the V112-3MW wind turbine, that will be installed in Olhava.

The order includes supply, installation and commissioning of the turbines and a six-year full-scope active output management agreement.

Vestas intends to complete the delivery of the wind turbines by the end of next year.

Vestas secured the first supply order for six similar units on 7 June 2011.

TuuliWatti Oy managing director Jari Suominen said Simo wind park, which will be finished at the end of this year, together with the new Ii-Olhava project, will bring a total capacity of 42MW to the market.