The workscope was on the TGT Field Development Project which is being developed by Hoang Long Joint Operating Company in the Cuu Long Basin, located 100km south east of Vung Tau.

Under the contract, EnerMech provided materials, equipment and personnel to carry out subsea hydrostatic leak testing on four flexible production risers, a water injection riser and two flexible gas risers.

The company also assisted with turret pipework removal and re-instatement, bolt tensioning/torquing, and lifting and rigging services.

EnerMech Asia Pacific regional director John Guy said the company provided a range of equipment and services, from hydraulic bolt tensioning and torquing for the topside scope, to subsea hydrotest equipment for the subsea flexible riser pre-commissioning work and lifting and rigging requirements.