This contract is in addition to the previously announced contract to supply coatings on the gas supply trunkline for the Wheatstone Project.

The combined value of the two contracts will exceed $170m.

As per the contract, the insulated flow lines will transport production from the offshore gas fields to the Wheatstone platform.

The gas supply trunk line will transport the produced gas from the Wheatstone platform to the Wheatstone LNG facility that will be located at Ashburton North in Western Australia.

The contracts will be executed at Bredero Shaw’s facilities in Kabil, Indonesia; Kuantan, Malaysia and Orkanger, Norway.

The scope of work includes coating approximately 300km of 10 to 44 inchdiameter pipe that will be protected with fusion bonded epoxy or three layer anticorrosion coatings, Thermotite polypropylene insulation coating, SureFlo internal coating and HeviCote concrete weight coating.

In addition, Bredero Shaw has also received a contract for anode procurement and installation as well as custom coating.

Work is scheduled to commence during the second quarter of 2012.