The project is located approximately 110km north-east of Aberdeen, Scotland, in 115m of water.
This contract, worth about EUR135m, features the reeling of mechanically lined pipe which provides a cost effective alternative for high temperature, highly corrosive materials.
Technip will be responsible for the engineering, procurement, installation and commissioning of two export, one production, one mechanically lined water injection and one gas lift flowlines.
The contract also covers one main umbilical and two subsea isolation valve umbilicals, subsea equipments, trenching and backfilling of all flowlines and umbilicals, and tie-ins, protection, pre-commissioning and commissioning support.
The project will be executed by the company’s operating centre in Aberdeen and will be completed in the second half of 2014.