The well was turned on to sales last week with a flow tubing pressure of 3250 psi and was heavily choked back to achieve a gas rate of 210,000 cubic feet of gas per day (210mcf/d).
This rate is being deliberately achieved while a compressor is installed to assist with the additional flow of gas from this new discovery.
Following the compressor installation, the well will be walked up to a stable production rate, and will be monitored and evaluated during this process.