The project is designed to maintain overall plateau production for the WDDM Concession, located 95 kilometers offshore Egypt in the Mediterranean.
Technip’s operating center in Oslo, Norway, will execute this contract with assistance from the group’s team in Cairo, Egypt. It covers turnkey delivery of the tie-in structure between a new gas export pipeline and two existing pipelines, including ‘hot tap tie-ins’ that allows the work to be carried out without stopping ongoing production.
Offshore installation is scheduled for the fourth quarter of 2010 using the Wellservicer, a vessel from Technip’s fleet.
BGC is a joint operating company of Egyptian General Petroleum Corporation (EGPC) 50%, BG Group 25% and Petronas 25% conducting oil and gas operations on behalf of the WDDM partners.
Technip provides project management, engineering and construction services to oil and gas industry.