The company had also retained the services of Oil and Gas Advisors, (OGA) to consult and assist with the completion efforts.
After a field visit and analysis earlier this month, Rob Dickinson, president of OGA proposed a solution for the remaining engineering issues that were present at the well site and also introduced the company to a well pump specialist with particular expertise in this region of the country and geologic formation.
Since that field visit and assessment, new equipment and hardware have been ordered and final work is expected to be completed within the next two to three weeks.
Steve Durdin, president and CEO of Indigo-Energy, said: “I am excited with the progress that we have made over the past several weeks. The experts that we have engaged for this project along with our field operating partners have done an outstanding job of isolating our remaining issues at the well site and have crafted a thorough work plan for all four of our wells in the Illinois basin.”