The ore concentrate has been shipped to Cameco’s facility at Blind River, Ontario, in September for further testing prior to sale.

The company is set to make a second shipment in mid-October to Canada.

Alliance said that the first shipment comprised 300,000lb, while second shipment contains 210,000lb.

Due to limited availability of maritime transport, the first shipment of uranium was delayed.

Located 550km north of Adelaide, the Four Mile project is a joint venture of Alliance Resources and Quasar Resources, which owns 75% of the mine. It was commissioned in March and was opened in June.

Alliance’s, Alliance Craton Explorer holds 25% of ML6402 and EL5017.