These tests involve pumping drilling fluids into the BOP to measure pressures and validate flow paths. When complete, a decision will be made on the execution of the top kill procedure itself, the company said.

According to BP, this top kill procedure has not been carried out offshore at 5,000ft water depth before, and its success cannot be assured. It is expected that the entire procedure could take up to two days, and it cannot be predicted how long it will take for the operation to prove successful or otherwise.

Should it be necessary, plans and equipment are in place to combine the top kill process with the injection under pressure of bridging material into the BOP to prevent or limit upward flow through the BOP, BP said.

The company said that it will continue to provide a live video feed from the seabed through the diagnostic testing and top kill, if undertaken. Throughout the diagnostic process and top kill procedure, significant changes in the appearance of the flows at the seabed will be expected. These will not provide a reliable indicator of the overall progress, or success or failure, of the top kill operation as a whole.

Should the top kill not succeed in fully stopping the flow of oil and gas from the well, BP will then intend to move forward to deployment of the lower marine riser package (LMRP) cap containment system.

Deployment of this system will involve first removing the damaged riser from the top of the BOP to leave a cleanly-cut pipe at the top of the BOP’s LMRP. The LMRP cap, an engineered containment device with a sealing grommet, will then be connected to a riser from the Discoverer Enterprise drillship and then placed over the existing LMRP with the intention of capturing most of the oil and gas flowing from the well.

The LMRP cap is already on site and it is anticipated that this option will be available for deployment by the end of May. Additional options also continue to be progressed, including the option of lowering a second blow-out preventer, or a valve, on top of the failed Deepwater Horizon BOP, BP said.

Work on the drilling of two relief wells, begun on May 2 and May 16, continues. Each of the wells is estimated to take some three months to complete from the commencement of drilling.