Besides the first five wells, GMX Resources has drilled Blocker Ware 19H with a 4,446 foot lateral and has concluded nine of 12 fracture treatments, thus far.

GMX Resources has also drilled and set casing on the Blocker Heirs 12H with a 4,934 foot lateral and TJT Simpson 1H with a 4,606 foot lateral. Planned completion for each of these two H/B Hz wells will follow the Blocker Ware 19H with 12 fracture treatment stages planned for each well. These wells are all anticipated to commence producing in second quarter 2009.