The company will deliver 70 units of its V90-2.0MW turbine and the contract includes supply, installation and commissioning of the turbines and a VestasOnline Business SCADA system.
Delivery of the turbines is scheduled to start in late 2011, with completion estimated for late 2012, and twenty-five of the 70 turbines will be installed in 2011.
Prokon develops renewable energy projects with a focus on wind power, and its total installed wind energy capacity is 385.9MW.