The company has paid about $75m for the project which will be located on 158 acres of land, about 30 miles southeast of Phoenix.
Construction of the PSEG Queen Creek solar farm is expected to begin this month and be completed in the third quarter of this year.
The facility will use crystalline panels and a single axis tracking system, and juwi will engineer, procure and construct the solar farm as well as perform operation and maintenance services for the project.
The electricity generated by the project will be purchased by the Salt River Project Agricultural Improvement and Power District for 20 years.