iomass is an emerging fuel source that is recognized as beneficial to climate change mitigation. The station is the largest power plant in North America fuelled by 100 per cent biomass.

"The conversion of Atikokan will ensure a clean, reliable, sustainable and local supply of electricity for the region," said Bob Chiarelli, Minister of Energy. "I am very happy to see this facility playing an active role in helping us deliver on the commitments in our Long-Term Energy Plan."

"Ontario is a leader in green energy production and technology and the conversion of the Atikokan Generating Station is a great example of innovative new opportunities available in Northern Ontario," said Bill Mauro, MPP Thunder Bay-Atikokan. "This facility will create and maintain well-paying jobs right here in our community and will contribute to Ontario’s clean energy strategy."

"Northwestern Ontario is on the leading edge of some very exciting new mining and forestry developments and I am very pleased that our government is taking action to meet the future energy needs of our region," said Michael Gravelle, MPP, Thunder Bay-Superior North. "This project is not only providing more clean power to Ontarians, it is creating promising new economic opportunities and sustainable jobs for Northwestern Ontario in the green energy and forestry industries."

"Northwestern Ontario is on the leading edge of some very exciting new mining and forestry developments and I am very pleased that our government is taking action to meet the future energy needs of our region," said Michael Gravelle, MPP, Thunder Bay-Superior North. "This project is not only providing more clean power to Ontarians, it is creating promising new economic opportunities and sustainable jobs for Northwestern Ontario in the green energy and forestry industries."

"The biomass conversion and solutions developed for the Atikokan GS are cutting edge and OPG is at the forefront of this innovative technology. The project is the first of its kind in Ontario and will bring economic benefits to northwestern Ontario for years to come," Mitchell added.

The Atikokan Generating Station (GS) conversion project got underway in mid-2012 with ground preparation and the construction of two silos, each 44 metres tall and 21 metres in diameter. Each silo can store up to 5,000 tonnes of wood pellets. Modifications to the boiler and a new Distributed Controls System were also required. As well, new truck receiving and transfer infrastructure was built.

Rentech Inc. and Resolute Forest Products Canada. Each will supply 45,000 tonnes of wood pellets annually for a total of 90,000 tonnes. Having two suppliers enhances reliability of supply. Both suppliers have employment arrangements with local Aboriginal communities. Transportation contracts are also in place.