The new 16-inch line will have future expansion capability of more than 200,000 barrels per day and include direct pipeline connections to producer tank batteries in Karnes and DeWitt counties.

A new station, likely near Helena, will connect into Koch Pipeline’s existing crude system in Pettus and Refugio.

Engineering for the new pipeline to connect Eagle Ford producers to Corpus Christi, Texas, has begun.

Koch Pipeline currently is building a line to expand delivery capability to Flint Hills Resources’ Ingleside waterborne terminal.

Koch Pipeline president Kim Penner said that the pipeline not only allows the company to ship more crude oil to Corpus Christi refiners and to the Flint Hills Resources waterborne terminal at Ingleside, but it also improves its efficiency and reliability as this project includes new tanks and a new truck station.