In Chhattisgarh, the company has received two orders from the Chhattisgarh State Electricity Board, for transmission line valued at INR0.77 billion.
The first order in Chhattisgarh is worth INR0.42 billion. The scope of the order involves supply of line materials and building 220 kilo watts (kV) DCDS Transmission Line from proposed 220 kV Substation Churi (Korba) to 220 kV Substation Bilaspur (Mopka) on turnkey basis. The total length of the line is 90 kilometers (kms) and the expected duration of the project is 19 months.
The second order in Chhattisgarh is worth INR0.35 billion. The scope of the order involves supply of line materials and supply and erection of construction of LILO of 400 kV S/C Korba – Bhilai (Khedamara) Line to 400 kV S/S Raipur (Raita) on turnkey basis. The total length of the line is 25 kms and the expected duration of the project is 8 months.