The Zitong-1 well reached total depth at 4,294m in the Xu2 Formation and the Yixin-2 well reached total depth at 4,165m in the Xu3 Formation.
The wells have been logged, Zitong-1 has been cased and cemented, and Yixin-2 is currently running casing prior to cementing.
A testing program for both wells is scheduled to commence in mid-December, Ivanhoe said.
Initial testing of the Zitong-1 well, located on the 70sq km Guan structure, is expected to commence in the Xu2 Formation.
At Yixin-2, an initial short-term flow test of the lower section of the Xu4 Formation will be performed, and the test data obtained will be used in the design of any ongoing stimulation program for this well.