GoldQuest Mining announced the results of an independent Pre-Feasibility Study (PFS), including maiden Mineral Reserves for its 100% owned Romero gold-copper project in the Dominican Republic.

With a Net Present Value ("NPV") of US$203 million, the PFS demonstrates the economic robustness of a proposed underground mine at Romero. All figures are in U.S. dollars unless otherwise stated, with a DOP/USD exchange rate of 46:1 and metal price assumptions of $1,300/oz gold (Au), $20/oz silver (Ag) and $2.50/lb copper (Cu).

PFS Highlights Include:

Maiden Probable Mineral Reserves of 7.03 million tonnes containing:

840,000 ounces of gold

980,000 ounces of silver

136 million pounds of copper

A 2,800 tonnes per day operation totalling life of mine gold equivalent production of approximately 1.117 Moz Au Eq

Annual gold equivalent production averaging 109,000 ounces per year

Post tax Net Present Value @ (5%) of $203 million (pre tax $317 million)

All-in Sustaining Cost of $595/oz Au Eq

Post tax Internal Rate of Return of 28% (pre-tax 38.6%)

Initial Capex of $158.6 (Life of Mine $250.9 including sustaining and closure)

"We are very pleased that our Romero PFS validates the previous Preliminary Economic Assessment studies and we look forward to aggressively advancing the project through permitting and final feasibility," stated Bill Fisher, Executive Chairman of GoldQuest. "Along with the robust PFS results, we are proud to have established the first Mineral Reserve in our district. We believe that the Romero mine as designed is only the starting point for the Company and that the remaining resources at Romero, Romero South and the exploration potential close by provides an excellent opportunity for growth beyond the mine plan in this PFS."

The PFS was prepared under the direction of JDS Energy & Mining Inc. ("JDS"), an industry-leading, international engineering firm, with extensive experience in both the construction and operation of mining projects. The study was supported by a team of internationally recognized firms, all of whom are independent of the Company, including:

Micon International Limited (Micon) (geology, mineral resources)

Golder Associates Limited (geotechnical, tailings and water management)

Allnorth Consultants Limited (process design)

MineFill Services Incorporated (backfill plant design)

The PFS envisages a 2,800 tonnes per day ("tpd") project, encompassing a ramp-accessed underground mining operation employing a standard crush, grind, flotation process plant to produce a saleable copper concentrate product with significant gold and silver credits. Process tailings will be used as paste backfill in the underground mine with excess material stored on site as dry stack material. Water requirements for the mine will be met by collecting and storing runoff water from the site.

Mineral Resource Estimate

The basis for the PFS is the updated mineral resource estimate prepared by Micon. Details of the resource estimate will be set out in the Company's upcoming National Instrument 43-101 ("NI 43-101") technical report for the PFS. For the purposes of reporting the mineral resources, Micon selected a net smelter returns ("NSR") cut-off of $60 (operating cost/commodity price weighted recovery) as an estimate of what might be a reasonable marginal cost of extraction at Romero and Romero South.

Mining

The mine plan for the Romero deposit contemplates a ramp accessible underground mine employing mechanized longhole and cut & fill stoping methods with both paste and waste rock for backfill. At full production, run of mine material will be transported to the surface at an average rate of 2,800 tpd where it will be hauled to the process plant, located approximately 3 km south of the mine. The PFS does not propose exploiting the Romero South deposit at this time. Romero South may be evaluated as a stand- alone deposit in the Feasibility Study stage.

The PFS mine plan includes 7.03 Mt grading 3.72 g/t Au, 0.88% Cu and 4.33 g/t Ag after accounting for dilution and mining recovery, with contained metal totaling 840k oz Au, 135.9 M lbs Cu (61.7 kt) and 980k oz Ag. The waste rock mined totals 900 kt, with all waste rock returned underground as backfill by Year 5.

The mine design includes a 5.0 m x 4.5 m ramp access with production coming from a combination of 75% longhole mining, 16% cut & fill mining and 9% from development. The mine scheduling targets the highest NSR sections of the deposit early in the mine life.

Processing

The processing flow sheet selected for the PFS consists of crushing, grinding, gravity and flotation to produce a 13% copper concentrate with gold and silver credits and no significant deleterious elements. A marketing study commissioned by the Company has demonstrated the saleability of this concentrate.

Approximately 40% of tailings will be used as paste backfill with the balance disposed of in a tailings storage area through dry stacking. Total recoveries into the final concentrates, based on existing metallurgical test work, are expected to be approximately 78.1% for gold and 94.6% for copper, and 58.6% for silver.

Infrastructure

Off-site infrastructure for Romero is planned to include a 23.5 km main access road connecting the site to the local, paved road network. In addition, a 24.5 km — 69 kV Transmission Line will connect the site to the national power grid.

Concentrate storage and handling would occur at the port of Puerto Viejo, which will host a storage shed for 15,000 tonnes of concentrate and a ship-loading conveyor system.

On site infrastructure includes;
· 2.8 km haul road between the portal and the process plant site;

Step-down transmission substation for incoming high voltage power from the national grid;

Fit-for-purpose ancillary facilities, including administration and offices, maintenance and warehousing, mine dry, assay laboratory;

Temporary Waste Rock Storage Area for 225,000 m3 of waste; and

Water storage pond, sedimentation ponds, dry stack and waste rock storage run-off collection ponds, and emergency pond for excess water.

Capital Costs

The pre-production capital cost for the project is estimated to be $158.6 million including indirect costs and contingency. Life of Mine ("LOM") sustaining capital is estimated at $92.3 million. Total LOM capital required for the project is approximately $240.9 million.

Life of mine sustaining capital costs are estimated at $81.7 million (excluding contingency) including the closure costs of $15.5 million. Sustaining capital consists of capitalized development after the initial production start-up and major equipment rebuilds.

Operating Costs

The operating costs used in the PFS were estimated from first principles using in-country unit rates for labour, consumables and power where possible. The LOM All-In Sustaining costs are estimated to be $595 per ounce of gold (payable net of by-product credits from copper and silver).

LOM site operating costs total $45.97/t processed, as summarized below.

These cost estimates assume an electricity rate of 0.12/kWh and a diesel cost of $0.66/L.

Financial Analysis

The summary below, showing a range of commodity prices, holds the above-noted electricity rate and diesel cost constant. The NPV figures are calculated to the beginning of 2018 when, assuming the receipt of necessary permits and approvals within expected timelines, construction would begin. For purposes of the calculations, any 2016 and 2017 development expenditures are treated as undiscounted costs.

Pre-Tax

Net Present Value (NPV) discounted at 5% is $317.2 M;

Internal Rate of Return is (IRR) is 38.6%.

Post-Tax

Net Present Value (NPV) discounted at 5% is $202.7 M;

Internal Rate of Return is (IRR) is 28.1%; and

Payback of 2.5 years.

Taxes modelled include a corporate tax rate of 27%, with Export Withholding Tax credited against gross corporate tax to generate net corporate tax. The Export Withholding Tax is applied at 5% on the Net Smelter Revenue, while a local community tax is applied 5% on taxable income. The net impact is an effective tax rate of approximately 32%.

Community and Environment

The PFS incorporates several important design features that minimize the impact to the surrounding environment:

The use of cyanide is not included in the design. A flotation concentrate product will be shipped from the Puerto Viejo port to international smelters;

100% of the waste rock from the underground mine will be returned back underground as backfill to eliminate the potential for acid rock drainage;

The project is designed to capture run-off water to supply the mine, thus avoiding any water taking from the San Juan river;

Tailings from the process plant will be filtered, dried and placed in a dry stack storage facility. No tailings ponds or dam structures will be required;

Power will be supplied by a line connection to the domestic power grid;

Ventilation fans will be located underground to reduce noise; and

No relocation of the Hondo Valle village, or any settlements.

Opportunities

There are a number of initiatives recommended which may further enhance the project economics, including:

Conversion of Inferred resources at Romero and Romero South to Measured and Indicated Mineral Resources which may be converted to Mineral Reserves

Examining resource growth potential at brownfields targets near Romero

Site investigation program for geotechnical, hydrology, hydrogeology and baseline environmental;

Additional drilling for metallurgical sampling and execution of further metallurgical testing on Romero South and pyrite concentrate product;

Discussions with smelters on terms and product specifications; and

Technical investigation of the Pueblo Viejo port and required upgrades.