Dzheitune (Lam) 13/144, which was drilled to a depth of 3,434mt on a single completion basis by Rig 40, tested at an initial rate of 1,809bopd. Rig 40 will now be cold-stacked on the Dzheitune (Lam) 13 platform and may be used for some additional workovers in future years.

Dzheitune (Lam) 28/146 which was drilled to a depth of 3,200mt on a single completion basis by the NIS rig, tested at an initial rate of 2,311bopd. This represents the first in a series of development wells to be drilled by the NIS rig from the Dzheitune (Lam) 28 platform. The NIS rig has now skidded to the next slot on the Dzheitune (Lam) 28 platform and has spudded the Dzheitune (Lam) 28/147 well.

The Iran Khazar rig has completed a sidetrack of the Dzheitune (Lam) A/129 well which was drilled to a depth of 1,815mt on a single completion basis and has yielded incremental production of 1,140bopd.

This completes the planned workover program for 2010. The Iran Khazar rig has since moved to the Dzheitune (Lam) B platform where it is planned to spud the Dzheitune (Lam) B/148 well, after first undergoing routine maintenance.

Dr Abdul Jaleel Khalifa, CEO of Dragon Oil, said: “I am delighted to report the successful completion and initial testing of both the Dzheitune (Lam) 13/144 and 28/146 development wells together with the sidetrack of the Dzheitune (Lam) A/129 well.

“This brings us to a total of six new development wells to date this year and we remain on target to complete 11 new wells in 2010.”