A subsidiary of Delta Power Services, a B&W company, has received a separate $19m, six-year contract to provide operations and maintenance services (O&M) for the facility.

The company will convert the former Fraser Paper Mill to a 75MW biomass energy power plant that will be fueled by wood chips and logging waste.

BWCC’s will engineer, procure and construct the facility and all associated balance of plant support systems, including the turbine/generator and fuel handling equipment.

The company will self-perform the erection of all B&W-supplied equipment and will begin engineering for the project immediately with start-up scheduled to begin in October 2013.

BWCC and its affiliated firms will design and supply material to convert the plant’s existing black liquor recovery boiler to a bubbling fluidized bed boiler, and design and supply ash handling equipment.

The companies will also design and supply the plant’s selective catalytic reduction system for nitrogen oxides control, a baghouse for the control of particulates emissions, a continuous emissions monitoring system and other plant equipment.