Domestic Nepalese hydro projects under development
|
Project name |
Capacity |
Project developer/ |
Status |
Commission |
|
(MW) |
finance |
|
|
Kali Gandaki A |
144 |
NEA/ADB + JBIC |
Construction |
March 2002 |
Middle Marsyangdi |
70 |
NEA/KfW |
Construction |
August 2004 |
Kulekhani 3 |
42 |
NEA/JBIC |
Engineering design |
2005 |
Chameliya |
30 |
NEA/Korea |
Engineering design |
Before 2010 |
Budhi Ganga |
20 |
Birla Corp, India |
Design/finance |
Before 2010 |
Kabeli A |
30 |
NEA/Word Bank |
Engineering design |
Before 2010 |
Likhu 4 |
51 |
Pacific Hydro, Aust |
Design/finance |
Before 2010 |
Tamur-Mewa |
101 |
Combined Energy, US |
Design/finance |
Before 2010 |
Rahughat Khola |
27 |
NEA/World Bank |
Engineering design |
Before 2010 |
Dudh Koshi 1 |
300 |
ASTQ Holding |
Design/finance |
Before 2010 |
|
|
Corp, Canada |
|
|
Kankai |
60 |
Coyne et Bellier, |
Design/finance |
Before 2010 |
|
France |
|
|
|
Sub-total |
875 |
|
|
|
Khimti Khola 2 |
27 |
Statkraft, Norway |
Feasibility |
|
Lower Arun |
308 |
Braspower, Brazil |
Feasibility |
|
Kali Gandaki 2 |
660 |
ASTQ, Canada |
Feasibility |
|
Upper Trisuli 2 |
300 |
Pacific Hydro, Australia |
Feasibility |
|
Mai Loop |
60 |
Sanimar Hydro, Nepal |
Feasibility |
|
Upper Marsyangdi 3 |
121 |
Sulzer Hydro, Switzerland |
Feasibility |
|
Sub-total |
1476 |
|
|
|
Total |
2351 |
|
|
|
|
|