“We’re still thinking about it and what it has and what issues that can be anticipated and whether the value of the energy is sufficient to cover the costs of the project,” said Dave Boyter, Symbiotics’ director of engineering and operations.

Dave said it’s still in the pre-preliminary phase of a lengthy process that could take around five years before a license is issued.

If the facility is built, Symbiotics would sell water-generated electricity generated from a powerhouse and three turbine-generators at the Stennis Dam.

The dam and TTW are operated by the U.S. Army Corps of Engineers. The use of the 234-mile canal is promoted by the Tennessee-Tombigbee Waterway Development Authority. Both agencies support the company’s plans.

“The TTWDA does not oppose such projects as long as it does not interfere with the navigability of the waterway,” said TTWDA Administrator Mike Tagert. Also, the company’s interest is indication and advantage of having constructed the waterway. As well, only healthy river systems are viable candidates for such plants, so this is a real testament to the health of this ecosystem.”

The hydropower facility would operate in a run-of-river mode using water-driven turbines with spinning blades producing electricity conveyed through a two-mile transmission line to the local utility’s distribution system.

“Hydropower is an important component of the nation’s energy portfolio and supports efficient, competitive electric markets by providing low-cost energy reserves and ancillary services,” FERC said.

“Hydropower projects also provide other public benefits, such as increased water supply, recreation, economic development and flood control, while minimizing adverse impacts on environmental resources.”

“Since 2001, we have been developing low-impact hydroelectric projects to meet the growing demand for renewable energy while preserving a healthy environment.”

While FERC has permitted Symbiotics to operate the 10 hydroelectric-generating facilities it now has, FERC rejected at least two company-proposed projects in Idaho as they would hurt the scenic Snake River’s environment.