Depending on the draw down of project contingencies, the final cost of the foundation project is expected to be 6% to 10% over the $11.2 billion approved by Woodside Petroleum at the time of the final investment decision in July 2007.

The expected increase in cost is due to lower than budgeted productivity in both onshore and offshore construction.