The TXP4 plant adds approximately 350 million cubic feet per day of natural gas processing and 30,000 barrels per day of natural gas liquid (NGL) production, roughly doubling Echo Springs’ capacity in both cases.

This expansion provides the ability to process currently flowing bypass gas as well as the ability to process expected future increases in third-party gas production.

Including this expansion, Williams’ Opal and Echo Springs processing plants in Wyoming have a combined daily inlet capacity of more than 2.1 billion cubic feet per day of natural gas and 130,000 barrels per day of NGL production capacity.

Williams is focused on natural gas transportation; gathering, treating and processing; storage; NGL fractionation; and oil transportation.