Enterprise will construct a new 17-mile, 20-inch diameter natural gas gathering pipeline originating at Anadarko’s central production facilities located in Dimmit County, Texas, and interconnecting with Enterprise’s existing South Texas pipeline system.
The services provided to Anadarko under these new six-year agreements include firm natural gas transportation and processing services utilizing Enterprise’s South Texas midstream infrastructure.
In addition to natural gas transportation and processing services, the NGLs recovered from Anadarko’s natural gas volumes will be transported and fractionated in Enterprise’s integrated NGL pipeline and fractionation assets throughout Texas.
Current processing capacity at Enterprise’s existing facilities in South Texas is 1.5 billion cubic feet per day, and an additional 600 million cubic feet per day is expected to be available in mid-2012 with the completion of a cryogenic gas processing plant in Lavaca County, Texas.