The company has also awarded ABB a contract to supply and install transformers and ancillary equipment for new substations at the Santander mine and at the interconnection to the Peruvian national grid.
Trevali Renewable Energy, a wholly owned subsidiary of Trevali Resources, is currently in the process of Phase-I upgrade of the 1.6MW Tingo power plant to 8.8MW generating capacity (approximately 10MW generation potential during wet season).
The Tingo hydroelectric plant is located 17km west of the Santander mine site.