The consortium has acquired an additional contract from Kruger Energie Bas-St-Laurent to supply power to Hydro-Quebec.
Kruger Energie transferred to the consortium the electricity supply agreement concluded with Hydro-Quebec in 2008.
The consortium carries out further stages of construction according to schedule for the first two wind farms at the Seigneurie de Beaupre site totaling an installed capacity of 272MW, and the commissioning of these projects is scheduled for December 2013.
The third wind farm is expected to be commissioned around December 2014.