Table 1: Plinth excavation quantities
Stage No / Access Route |
Elevation |
Start date |
Finish date |
Qtty (m3). |
Stage 4, Access Road 5, P15 to P12 |
322 |
16 Dec 2003 |
03 Jan 2004 |
52,989 |
Stage 5, Access Road 4, P11 to P12 |
222 |
05 Jan 2004 |
07 Apr 2004 |
80,805 |
Stage 9, Access Road 4, P10A to P11 |
222 |
28 Aug 2004 |
21 Sep 2004 |
34,360 |
Stage 1, Access Road 1, P1 to P3 |
400 to 385 |
29 May 2003 |
30 Jun 2003 |
35,300 |
Stage 2, Access Road 2, P3 to P6 |
385 to 335 |
02 Jun 2003 |
07 Oct 2003 |
42,542 |
Stage 3, Access Road 3, P6 to P7 |
335 to 269 |
07 Oct 2003 |
15 Dec 2003 |
23,428 |
Stage 7, Access Road 3, P7 to P8 |
335 to 269 |
12 Mar 2004 |
05 Apr 2005 |
15,619 |
Stage 6, Access Road 4, P8 to P9 |
269 to 222 |
09 Feb 2004 |
17 Mar 2004 |
85,002 |
Stage 8, Access Road 4, P9 to P10A |
222 to 208 |
04 Apr 2004 |
29 Apr 2004 |
21,877 |
Total Excavation (m3) |
|
|
|
391,922 |
|