The company will engineer, supply, construct and commission the 1000 MW supercritical steam turbine and generator, the supercritical boiler, power plant auxiliaries such as mills and air-pre-heaters as well as proprietary environmental control systems.

Alstom will also supply and install its latest ALSPA Series 6 Distributed Control System, low NOx burners, a seawater flue gas de-sulphurisation facility and fabric filters.

Alstom’s share in the contract amounts to EUR830m.

The Tanjung Bin power plant will be operation by 2016.