Allegheny Power is completing nearly $60m in infrastructure improvements and new construction in Maryland over the past two years.

Rodney Dickens, president of Allegheny Power, said: “Our primary responsibility is to ensure that reliable electricity is available at a flip of the switch or push of a button – regardless of whether it’s a sweltering summer day in Frederick or a snowy winter night in Cumberland.

“We are continuously working to monitor, maintain and improve Allegheny’s electric system in order to provide our customers with high quality service.”

The company’s service reliability programme includes inspection and preventative maintenance of lines, substations and other electrical equipment; investment in infrastructure improvements; tree trimming; employee training; and testing and updating of operations and support systems.

Infrastructure upgrades in Maryland include $24m in transmission and distribution investment for installing new service or expanding existing service for customers; $14m for transmission line and substation projects, excluding the new PATH transmission line project; $10m for distribution maintenance and reliability improvement projects; and $10m for replacing distribution equipment, such as overhead lines, underground cable, meters and utility poles.

Among the critical projects completed in The Old Line State were converting the 138kV transmission system to a higher capacity 230kV system in Frederick and Montgomery counties;

replacing conductors on a 230kV transmission line in southern Frederick and Montgomery counties; replacing transformers at substations near Petersville, Point of Rocks and Thurmont; new circuits and upgrades in the Hagerstown area to address commercial and residential load growth; upgrading underground cable in 26 locations in the Frederick, Mount Airy and Thurmont area; installing additional fuses, switches and fault indicating devices on more than 90 distribution circuits throughout the service territory; and construction of a new substation at the former Fort Richie Army Base near Cascade is scheduled for completion by the end of 2009. The substation is designed to support commercial development at the site.

The company’s investment for infrastructure improvements and new construction in 2008 and 2009 in its four-state service territory will total approximately $360m, excluding the TrAIL and PATH transmission line projects.