The key objective of the project, which is being developed at the Gordon Creek natural gas project in Utah, US is to store up to one million tons of CO2 per year.

The initial focus of the field activities will include an extensive 3D seismic shoot in order to gain further understanding of the structure that is believed to host the previously discovered CO2 at Gordon Creek.

The activities will also include to optimize the location of the initial CO2 source well to be drilled in 2012.

The project will also be re-working the existing injection well at Gordon Creek in order to conduct a high rate combine CO2-water injectivity test.