* % figure relates to the 1300m drill and blast section. The balance will be bored by one of the TBMs ** % figure relates to the 700m drill and blast section. The balance will be bored by one of the TBMs
Contract
Progress to date
Percentage
Total size
Diversion tunnel 1, main dam site
Complete
100
752m
Diversion tunnel 2, main dam site
Complete
100
835m
Adit 1, Teigsbjarg escarpment
Complete
100
1258m
Adit 2, Axar river
1302m
100
2800m*
Adit 3, Glmstadadalur valley
369m
53
2650m**
Hlsln power intake
120m
Headrace tunnel from adit 1
357m
39,756m
Main dam fill
488,400m3
5.8
8.5Mm3
Coffer dam fill
49,420m3
90.1
55,000m3
Fljtsdalur valley access tunnel
962m
99.7
1000m
Fljtsdalur valley cable tunnel
769m
84.5
1000m
Fljtsdalur valley tailrace tunnel
603m
45
1100m
Sign up for our weekly news round-up!
Give your business an edge with our leading industry insights.
I consent to Verdict Media Limited collecting my details provided via this form in accordance with Privacy Policy
Vist our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of
your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.