Tyrihans seabed installations

Four production frames, A, B, C and D will hold 12 production and gas injection wells and four available slots. All frames will be connected to a 42.6 kilometer long production pipeline (16 feets) to Kristin.

Gas for gas injection and gas lift in the production wells will come from a 10 feet pipeline from Asgard B.

Start-up of the first production well to Kristin, as well as gas injection from Asgard B, is planned for July 1, 2009. The gas injection is planned to last until 2015. Injection of sea water will commence in 2010 and last until 2016.